Existing Site Conditions

The club drive property is an undeveloped lot adjacent to the District’s Ascencion Solorsano Middle School. As part of the previous GUSD bond program a new elementary school was proposed on the site. However, the development was canceled due to the changing needs of the District.

While the site is currently vacant, it presents a strategic opportunity to advance the District’s long-term goals.

Immediate Needs (0-5 Years)

  • Design and build Phase 1 of soccer sports complex with multiple natural turf fields, gravel parking and restrooms. This project will be designed to open as fast as possible with Phase 2 being more permanent construction.

Long Term Needs (5-10 Years)

  • Implement Phase 2 of the soccer sports complex with permanent restrooms, snack shack, paving, sports lighting, playground.

Existing and Proposed Site Plans

Community Engagement Feedback

Mental Health and Social Emotional Needs

If one improvement could be made to help support student mental health and wellness, what would it be?

“I believe the wellness programs are out in a portable. It would be nice to have it more centrally located and in a permanent room rather than a portable.”

Student / Parent
Student / Parent
“I would love more activities outside of normal school hours to do. One year Ms. Lazono did a yoga/wellness class and the kids raved about it. Would love that again.”
Student / Parent
Student / Parent
“I believe the wellness programs are out in a portable. It would be nice to have it more centrally located and in a permanent room rather than a portable.”
Student / Parent
Student / Parent

Cost Estimate

Site
Club Drive

Immediate Needs (0-5 Years)

See Fields

Facility Condition Index (FCI)* (5 Years)

n/a

Long Term Needs (5-10 Years)

$6,167,392

Facility Condition Index (FCI)* (10 Years)

n/a

New Construction

$4,188,600

Deferred Maintenance

n/a

Sport Fields & Playgrounds

$12,781,316
Total Site Project Cost (0-5 Years)***
$23,962,525
Total Site Project Cost (5-10 Years)****
$32,067,264

*** Total Project Costs Include:
Base Construction Cost + Contractor Mark Up (30%) + Soft Costs (44%) w. Escalation (5yr)
****Total Project Costs Include:
Base Construction Cost + Contractor Mark Up (30%) + Soft Costs (44%) w. Escalation (10yr)

* FCI Ratings:
0-5% In new or well-maintained condition, with little visual evidence of wear or deficiencies.
5-10% Subjected to wear but is still in a serviceable and functioning condition.
10-30% Subjected to hard or long-term wear. Nearing the end of its useful or serviceable life.
30% and Above Has reached the end of its useful or serviceable life. Renewal is now necessary.